From any of your projects, build an S-Curve cost prediction curve. (Project can be making a sandwich)
Assignment 3:
Given the following resources and the following PDM Chart, build a predictive PRODUCTION S-Curve for this short schedule. Show ES/LS unit productions. Make sure the scale is large enough to be seen. Build the chart by free-hand drawing if you would like or use Excel charting capacity, or scan and send an Excel file.
Note: Base your diagram on Late Finish Dates and for each activity use uniform work over time.300 widgets/5 days = 60 widgets per day for activity 2.
Hint: Work backward from the end date when making your spread sheet from above.
Activity 1 600 widgets
Activity 2 300 widgets
Activity 3 1200 widgets
Activity 4 45 widget
Note: The assignment only asks about planned production.
For real predictive capacity you would overlay experienced (measured) inputs (costs) and experienced actual (measured) outputs (widgets).