Real-life project

Pick a real-life project (e.g., COVID related, setting up a business, house construction,…). For
this project, discuss among your group (also discuss with experts in that field) and come up with
a list of activities to be accomplished. For each of the activities identify the predecessors. Based
on your group discussion and experts’ advise; set the optimistic, most likely, and pessimistic time
to accomplish each activity.
Once you have the above information, compile a report providing your analysis including the
following:
a. A project network for your project.
b. The Earliest starting (ES), Earliest finishing (EF), Latest starting (LS), and Latest finishing
(LF) time of each project activity. Explaining the purpose of identifying this information
(Hint: Allowing vacation time for workers).
c. Identifying the critical path, and the critical activities of your project.
d. Estimation of the expected time to complete your project.
e. Estimation of the probability that your project will be completed within 2 Months (9 weeks
or 60 days)?