Project sponsor and the stakeholders
Create a 5-to-8-minute video for your project sponsor and the stakeholders that are director and above (there will be vice presidents there as well).
Important to note you are three months into the project. At least one identified risk has occurred which impacted your schedule and budget. The risk also created 5 new issues that are impacting the project (be creative on the types of risks and issues).
List the top 3 risks.
Make sure to provide earned value statistics for your project.
Make sure to let the audience know what tasks are expected to get done in the next month.
Sample Answer
Project Update: Progress, Risks, and Next Steps (5-8 Minutes)
Introduction (0:30)
Good morning everyone, and thank you for joining this project update. Three months in, we’ve made significant progress, but it’s important to be transparent about both our achievements and challenges.
Project Overview (1:00)
[Briefly summarize the project goals and key milestones achieved so far. Use visuals like charts and diagrams where appropriate.]
Earned Value Analysis (1:30)
Our Earned Value Analysis shows: