Based on feedback from your WBS submission, and the readings you have completed, refine your WBS and create a Task Plan.
Tasks are the most basic building blocks of any project - tasks represent the work to be done to accomplish the project deliverables. They are units of
work to accomplish the Charter. Each task must be:
Measurable: Can it be measured and tracked?
Assignable: Can it be assigned to one or more people to perform?
Work independent: Is it separable enough to avoid confusion, accountability, and measurement?
Like your WBS, Task Plans are hierarchal in nature. It is important to remember that the 100% rule applies to the activity or task level too. The work
represented by the activities in each work package must add up to 100% of the work necessary to complete the work package.